Redesign Road Project Using Critical Chain Project Management Method and Crashing Method
DOI:
https://doi.org/10.31315/opsi.v14i2.5651Keywords:
Critical Chain Project Management, Crashing, Jalur Pekerjaan Kritis, PenjadwalanAbstract
Construction of the Provincial road project from Parigi to Sukamanah is carried out by PT. Jaya Madiri Konsulindo as consultant and PT. Karya Tunas Mandiri Persada as contractor. The problem of the construction project is implementation duration does not match to previous planning which results delay in completion time. It is necessary to re-plan the project in order to get either optimal time or cost. The purpose of this research is to find out the critical work path using critical chain project managemet method by utilizing microsoft project software and optimization of project time and cost using crashing method with alterative increase of working hours (overtime) and addition of labor. The research’ scope is limited on labor cost only. Based on the results of the study obtained that initial labor wage cost is IDR 585,025,000.00 with a working duration of 154 days, and results of the alterative crashing method is lower with labor wage cost IDR 576,750,000.00. It could save cost about IDR 8,275,000.00 with duration of work 150 days or earlier 4 days from the initial duration.
References
Araszkiewicz, K. (2017). Application of Critical Chain Management in Construction Projects Schedules in a Multi-Project Environment: A Case Study. Procedia Engineering, 182, 33–41. https://doi.org/10.1016/j.proeng.2017.03.108
Elisabeth Riska Anggraeni, D. (2017). Analisis Percepatan Proyek Menggunakan Metode Crashing Dengan Penambahan Tenaga Kerja dan Shift Kerja (Studi Kasus : Proyek Pembangunan Hotel Grand Keisha, Yogyakarta). Journal of Engineering Research and Applications, 605.
Giri, F., Ningrum, A., & Hartono, W. (2017). PENERAPAN METODE CRASHING DALAM PERCEPATAN DURASI PROYEK DENGAN ALTERNATIF PENAMBAHAN JAM LEMBUR DAN SHIFT KERJA ( Studi Kasus : Proyek Pembangunan Hotel Grand Keisha , Yogyakarta ). 583–591.
Mandiyo Priyo, S. S. (2017). Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi : Studi Kasus Proyek Jalan Bugel-Galur-Poncosari Cs. Tahap I, Provinsi D.I. Yogyakarta . Semesta Teknika, 20(2), 172–186.
Ningrum, F. G. A., Hartono, W., & Sugiyarto. (2017). Pengertian Metode Crashing Dalam Percepatan Durasi Proyek. E-Jurnal MATRIKS TEKNIK SIPIL, 3.
Olivia, P., & Puspasari, V. H. (2019). Analisa Percepatan Waktu Proyek Menggunakan Metode Crashing (Studi Kasus : Peningkatan Jalan Pelantaran – Parenggean – Tumbang Sangai). Jurnal Teoritis Dan Terapan Bidang Keteknikan, 3(1), 41–52.
Priyo, Mandiyo dan Aulia, M. R. (2016). Aplikasi Metode Time Cost Trade Off Pada Proyek Konstruksi : Studi Kasus Proyek Pembangunan Gedung Indonesia. Semesta Teknika, 18(1), 30–43.
Putra, Y., & Hartati, S. (2017). Optimalisasi Waktu Dan Biaya Menggunakan Metode Least Cost Analysis Pada Proyek Peningkatan Jalan Lingkar Kota Dumai. Jurnal Saintis, Vol. 17 No(April), 100–112.
Ramang, R., Frans, J. H., & Djahamouw, P. D. K. (2017). Faktor-faktor keterlambatan proyek jalan raya di kota kupang berdasarkan persepsi stakeholder. Jurnal Sipil Statik, VI(1), 103–116.
Setiawan, S., Syahrizal, & Dewi, R. A. (2017). Penerapan Metode CPM Dan PERT Pada Penjadwalan Proyek Konstruksi.
Sinaga, T., & Husin, A. E. (2021). Analysis of Time Efficiency with CCPM Method and BIM in Construction Projects Construction of High-Rise Residential Building Basement. Civil Engineering and Architecture, 9(5), 1465–1477. https://doi.org/10.13189/cea.2021.090519
Sulistyo, A. B., & Fikri, M. Al. (2021). PROYEK KONSTRUKSI MENGGUNAKAN METODE TIME COST TRADE OFF ( STUDI KASUS : PROYEK PEMBANGUNAN JALAN GORDA-BANDUNG ). 4(1), 25–40.
Tegar, M., Aji, J., Sari, S. N., Studi, P., & Sipil, T. (2020). Analisis Biaya Percepatan Dengan Metode Time Cost Trade Off Di Pasar. 01(01), 63–72.
Downloads
Published
Issue
Section
License
Authors who publish articles in this journal agree to the following conditions:
- Copyright remains with the author and gives the Opsi journal the right as a priority to publish its articles with Creative Commons Attribution 4.0 International license. Which allows articles to be shared with acknowledgement of the author of the article and this journal as the place of publication.
- Authors can distribute their articles on a non-exclusive basis (e.g. in university repositories or books) with notification or acknowledgement of publication in Opsi journals.
- Authors are allowed to post their work online (e.g. on a personal website or in a university repository) before and after the submission process (see The Effect of Open Access)
This work is Licensed Under a Creative Commons Attribution 4.0 International license.